Much faster building permits and grid connections
https://metamachine.sukanthoriginal.com/guide/idea-permits-grid-fast.html

A permitting and grid-connection process that grants building permits in about 1 month and grid connections (and other major infrastructure approvals) in about 12 months, adopted by governments from 2027, so the cost of waiting falls from about 6.8 to about 1.6 cents per dollar of construction (2026 int$ of waiting cost per $ of construction, C13).

Result
Measure | Value | 
Share of the gap filled, median across the draws | 0.18% | 
80% range | 0.0% to 1.1% | 
Dollars a year in 2035 (median) | $0.3T | 
Growth points a year (median) | 0.01 | 
Median economy, the entry as written | 0.33%: $0.5T tier 1, $0B tier 2 | 
What people buy (path a), above on course | $0.5T | 
What inputs allow (path b), above on course | $37.1T | 
What limits it | buyers | 
Runs short next, across the 1,000 runs | Cropland in 52.6%; Construction trades in 26.9%; Physical machine labour (robots) in 20.5% | 
Runs short next, middle case (the receipt) | Physical machine labour (robots), then Cropland | 
Share of its market using it in 2035 | 14.3% | 
Price against the next-best option | 0.0158 against 0.0675 (2026 int$ of waiting cost per $ of construction (C13)) | 
Value to people beyond measured GDP (not added) | $73B | 
Possible extra from unsourced knock-ons (not added) | $0B | 
Starting numbers both ways (A2): stage1-v5 / replaced | 0.33% / 0.33% | 
Trust | low: method within 2x on 2 of 5 past cases; known effect inside its 80% range in 3 of 5; weakest key number [A] (7 of 10 key numbers assumed); no key number rests on a saved source | 
Receipt
Step | What | Units on course | Units with | Old price | New price | Gain | 
a | permits_grid_fast d1: cost on new:permit_wait ($ of construction (C13) a year, at today's construction prices) | 69,696,885,958,744 | 70,215,091,025,111 | 0.0675 | 0.0158 | $0.5T | 
b | permits_grid_fast ch1: supply K01 |  |  |  |  |  | 
result | path (a) on course + gains |  |  |  |  | $290.7T | 
result | path (b) most output before K04 passes its record-pace supply |  |  |  |  | $327.3T | 
result | result = smallest of (a), (b), target; minus on course = gap filled (buyers limit) |  |  |  |  | $0.5T | 
What would change this answer
Number | Label | Gap at low | Gap at high | Evidence that would settle it | 
available_year | A | 2.1% | 0.0% | [A] now. Settled by a study of when it is available. | 
spread.years_10_to_90 | A | 1.6% | 0.09% | [A] now. Settled by a study of how fast comparable products spread from 10% to 90% of buyers. | 
next_best.price | A | 0.11% | 0.77% | [A] now. Settled by a study of today's price of the next-best option. | 
For the profit-machine: gross value added in 2035 $99B; price against the next-best option 23.3%; capital per dollar of output 0.5.
At other prices
Price | Share of the gap, median (80% range) | Limit | Runs short next | Beyond the demand evidence | 
0.0675 | 0.0% (0.0% to 0.32%) | buyers | Physical machine labour (robots) | no | 
0.054 | 0.01% (0.0% to 0.49%) | buyers | Physical machine labour (robots) | no | 
0.0405 | 0.06% (0.0% to 0.67%) | buyers | Physical machine labour (robots) | no | 
0.027 | 0.13% (0.0% to 0.87%) | buyers | Physical machine labour (robots) | no | 
0.0169 | 0.17% (0.0% to 1.1%) | buyers | Physical machine labour (robots) | no | 
0.0158 | 0.18% (0.0% to 1.1%) | buyers | Physical machine labour (robots) | no | 
0.0101 | 0.19% (0.0% to 1.2%) | buyers | Physical machine labour (robots) | no | 
0.00675 | 0.21% (0.0% to 1.3%) | buyers | Physical machine labour (robots) | no | 
0.00338 | 0.22% (0.0% to 1.4%) | buyers | Physical machine labour (robots) | no | 
0.00135 | 0.23% (0.0% to 1.4%) | buyers | Physical machine labour (robots) | no | 
0.000675 | 0.23% (0.0% to 1.4%) | buyers | Physical machine labour (robots) | no | 
6.75e-05 | 0.23% (0.0% to 1.4%) | buyers | Physical machine labour (robots) | no | 
The research agent's comparison with published estimates
# permits_grid_fast: comparison with published estimates
**Machine (world, 2035, waiting cost 1.6 instead of 6.8 cents per $ of construction):** median across draws $291B a year, 0.10% of world GDP, 0.01 growth points (80% range $0-1.8T). As written: $527B (0.18%).
**What it is made of:** the waiting saving on the 14.3% of construction reformed by 2035, about half from building permits (5 to 1 month) and half from grid and major-infrastructure approvals (45 to 12 months). At full uptake (90%) it would be $3.2T (1.1%): infrastructure $1.55T (0.54%), power projects alone about $0.8T.
**Sources:** all figures are from search snippets only: unsaved, strength 3 at best.
| Estimate (strongest first) | Their figure | Machine's same measure | Machine / it |
|---|---|---|---|
| CEA, Oct 2026 | US long-run GDP +0.28-0.56% if reviews fall from 4.2 to 2 years; +0.41-0.83% at 1 year | infrastructure part: 0.54% at full uptake; ~0.085% in 2035 | 0.65-1.3x; 0.1-0.2x in 2035 |
| Hsieh-Moretti 2019 | US GDP +3.7% (2009) from looser land-use rules in three metros | 1.1% at full uptake; 0.18% in 2035 | 0.3x; 0.05x |
| RFF, Power Delayed | US net cost of power-project delays $47bn (scenario total) | power part ~$0.8T a year (world, full uptake); a US tenth ~$80bn | >1.7x (theirs is a total) |
| C2ES-cited study (new) | US transmission reform: $125bn of grid costs saved 2026-2040 (~$8bn a year) | as above | \u226510x |
| Grid Strategies and Brattle (new) | fixing interconnection: ~$100bn of benefits; PJM delay costs up to $7bn in a year | as above | ~11x (PJM, yearly) |
| McKinsey | $1.7-2.4T of cumulative US GDP forgone in federal permitting | a stock with no period: not convertible | - |
## Gaps over 2x
- **CEA in 2035:** spread. The CEA is long-run full adoption; the machine reaches 14% of construction by 2035 (12 years from 10% to 90% [A]). At full uptake its infrastructure part is inside the CEA's range for a similar wait cut (38 months against 33).
- **Hsieh-Moretti:** a channel the machine lacks: how much may be built where workers are most productive (zoning), not how fast. The model has no geography.
- **Grid studies (machine 2-10x or more higher):** a different measure, and likely a machine overstatement.
  - The studies count electricity-system costs, US or regional, often cumulative.
  - The machine charges the return on the whole project's value for each month of waiting, though before construction only land, design and finance are tied up (red team RT16), so its grid part is probably too high.
  - Its extra electricity is not valued (power does not bind).
## Which I trust more
**Major infrastructure:** both, since the CEA and the machine agree for a similar wait cut.
**Grid connections:** the electricity-system studies; no study backs the machine's waiting cost for pre-construction queues.
**Building permits (half the machine's gain):** no published GDP estimate exists; the machine rests on the practitioner rule of about 1% of cost a month (strength 3).
**The 2035 number:** low trust (7 of 10 key numbers assumed); most of its uncertainty is how fast governments adopt the reform, which no estimate addresses.

Sources
Source | Strength | Saved copy | 
LBNL, Queued Up: 2026 Edition (Rand et al., June 2026); saved copy from stage1-v2/v1/agent (https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf) | 1 | yes | 
LBNL, Queued Up: 2026 Edition; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_qu (https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf) | 1 | yes | 
LBNL, Queued Up: 2026 Edition; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_qu (https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf) | 1 | yes | 
LBNL, Queued Up: 2026 Edition; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_qu (https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf) | 1 | yes | 
LBNL, Queued Up: 2026 Edition; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_qu (https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf) | 1 | yes | 
IEA, World Energy Outlook 2025; saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo20 (https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf) | 1 | yes | 
IEA, World Energy Outlook 2025 (data-centre connection queues); saved copy from stage1-v2/ (https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf) | 1 | yes | 
IEA, World Energy Outlook 2025 (data centres at risk of delay); saved copy from stage1-v2/ (https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf) | 2 | yes | 
IEA, World Energy Outlook 2025 (power investment); saved copy from stage1-v2/agent4_bottle (https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf) | 1 | yes | 
Albouy, Ehrlich and Liu (2016), Housing Demand, Cost-of-Living Inequality, and the Afforda (https://www.nber.org/system/files/working_papers/w22816/w22816.pdf) | 2 | yes | 
Albouy, Ehrlich and Liu (2016), NBER WP 22816, cross-metro estimate; saved copy from stage (https://www.nber.org/system/files/working_papers/w22816/w22816.pdf) | 2 | yes | 
IRENA, Renewable Power Generation Costs in 2024 (summary), Table S1; saved copy from stage (https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2025/Jul/IRENA_TEC_RPGC_in_2024_Summary_2025.pdf) | 1 | yes | 
IRENA, Renewable Power Generation Costs in 2024 (summary), Table S1; saved copy from stage (https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2025/Jul/IRENA_TEC_RPGC_in_2024_Summary_2025.pdf) | 1 | yes | 
IRENA, Renewable Power Generation Costs in 2024 (summary), capacity additions; saved copy  (https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2025/Jul/IRENA_TEC_RPGC_in_2024_Summary_2025.pdf) | 1 | yes | 
Soltas et al. (2026), permit records for 60 US cities 2000-2025 (Princeton / University of (https://www.multihousingnews.com/why-permitting-time-has-doubled-since-2000/) | 2 | search only | 
Soltas et al. (2026), as reported by Multi-Housing News; search snippet only (https://www.multihousingnews.com/why-permitting-time-has-doubled-since-2000/) | 2 | search only | 
World Bank, Doing Business 2020, United States economy profile (dealing with construction  (https://subnational.doingbusiness.org/content/dam/doingBusiness/country/u/united-states/USA.pdf) | 1 | search only | 
World Bank, Doing Business 2012, Dealing with construction permits chapter; search snippet (https://www.doingbusiness.org/content/dam/doingBusiness/media/Annual-Reports/English/DB12-Chapters/Dealing-with-construction-permits.pdf) | 1 | search only | 
World Bank, Doing Business, Dealing with construction permits chapters (reform counts); se (https://subnational.doingbusiness.org/content/dam/doingBusiness/media/Annual-Reports/English/DB14-Chapters/DB14-Dealing-with-construction-permits.pdf) | 1 | search only | 
National League of Cities, Housing Supply Fact Sheet 5 (citing a Washington State study, a (https://www.nlc.org/wp-content/uploads/2025/09/Housing-Supply-Fact-Sheet-5.pdf) | 3 | search only | 
Sightline Institute, citing Seattle planners' analysis of permitting delay; search snippet (https://www.sightline.org/?p=61333) | 3 | search only | 
CBO Working Paper 2026-10, A Model for Estimating the Economic Effects of Changes in Permi (https://www.cbo.gov/publication/62517) | 2 | search only | 
Council of Economic Advisers, The Economic Benefits of Permitting Reform (October 2026); s (https://www.whitehouse.gov/research/2026/10/the-economic-benefits-of-permitting-reform/) | 2 | search only | 
McKinsey, Unlocking US federal permitting: A sustainable growth imperative; search snippet (https://www.mckinsey.com/industries/public-sector/our-insights/unlocking-us-federal-permitting-a-sustainable-growth-imperative) | 3 | search only | 
Hsieh and Moretti (2019), Housing Constraints and Spatial Misallocation, American Economic (https://eml.berkeley.edu//~moretti/growth.pdf) | 2 | search only | 
Resources for the Future, Power Delayed: the hidden costs of postponing power projects (Re (https://resources.org/resources-radio/power-delayed-the-hidden-costs-of-postponing-power-projects-with-mckenna-peplinski) | 2 | search only | 
Mayer and Somerville (2000), Land use regulation and new construction, Regional Science an (https://realestate.wharton.upenn.edu/wp-content/uploads/2017/03/331.pdf) | 1 | search only | 
Resources for the Future, Report 26-11 (EPA 2023 social cost of carbon in 2026 dollars); s (https://media.rff.org/documents/Report_26-11_Final.pdf) | 2 | search only | 
Sources - results/summary.csv (https://metamachine.sukanthoriginal.com/data/v7/results/summary.csv) - results/receipts.csv (https://metamachine.sukanthoriginal.com/data/v7/results/receipts.csv) - results/sensitivity.csv (https://metamachine.sukanthoriginal.com/data/v7/results/sensitivity.csv) - results/runs.csv (https://metamachine.sukanthoriginal.com/data/v7/results/runs.csv) - capabilities/permits_grid_fast.yaml (https://metamachine.sukanthoriginal.com/data/v7/capabilities/permits_grid_fast.yaml)