# Starter 6 (stage1-v7, Part B2). Written by the research agent (full path, batch run, 2026-11-18).
# Research log: pitch/logs/grid_equipment_fast.md. Every number: value, unit, label (S/E/A), sources, derivation.
id: grid_equipment_fast
name: Transformers and grid equipment built far faster
category: faster
path: full
pitch: "Transformers and grid equipment built far faster (faster)"
restated: "Transformers, switchgear and other grid equipment made and delivered in about a month (today large power transformers take two to four years), available from 2028, so power plants, grid lines and data centres no longer stand idle waiting for their equipment: the waiting cost falls from about 6.0 to about 0.75 cents per dollar of equipment in those projects (2026 int$ of waiting cost per $ of equipment in grid-connected projects, C14)."
price:
  value: 0.0075053
  unit: "2026 int$ of waiting cost per $ of equipment in grid-connected power, grid and data-centre projects (C14)"
  label: A
  sources: []
  derivation: "Batch run, no user to ask: the price is assumed. The pitch is about speed, so the price is the lead time turned into money: T1 = 1 month of waiting for equipment on the project's critical path [A] (derivation_inputs.T1_eq) x the cost of a month of waiting m_month = 0.0075053 [E] = 0.0075053. 1 month: 'far faster' read as equipment made to stock or in weeks, as distribution transformers were before 2020 (4 to 6 weeks, or 1 to 3 months, search snippets, A). The runs sweep this from the next-best price down to near zero."
next_best:
  name: "Today's transformer and grid-equipment supply: large power transformers average about 128 weeks (Wood Mackenzie, Q2 2025), against 30-60 weeks before the pandemic; the median US power project took 31 months from interconnection agreement to operation in 2025 against 21 months in 2008. Taken as about 8 months of waiting for equipment on the average grid-connected project's critical path."
  price:
    value: 0.060043
    unit: "2026 int$ of waiting cost per $ of equipment in grid-connected power, grid and data-centre projects (C14)"
    label: A
    sources: [lbnl_iacod2008, lbnl_iacod2025, lbnl_iacod_why, iea_leadtimes, wm_leadtime128, wm_prepandemic]
    derivation: "T0 = 8 months [A] (derivation_inputs.T0_eq) x m_month = 0.0075053 [E] = 0.060043. A, because T0 is assumed; its anchors are sourced (LBNL: +10 months from agreement to operation 2008-2025, S; IEA: lead times for large power transformers nearly doubled, S)."
performance: "The same transformers, switchgear and cables, made and delivered in weeks instead of years, so grid-connected projects (power plants, grid lines and substations, data centres) start operating as soon as the rest of the project is ready. It needs more factory capacity for transformer windings and cores (grain-oriented electrical steel, copper: copper was about 10% of a power transformer's price in 2023, IEA), test bays and skilled workers; companies have announced capacity increases of about 50% within about 15 months (search snippets), which is the kind of ramp 'far faster' assumes, repeated across the industry. It is not a new technology. Prices of power transformers almost doubled since 2019 (IEA); with ample capacity they would fall back toward their cost, but that fall on equipment bought anyway is mostly a transfer from makers to buyers, not a gain, so it is not counted (see not_mapped). The gain counted is the idle time saved. No physics limit is involved."
available_year:
  value: 2028
  unit: year
  label: A
  sources: [vt_rincon, siemens_charlotte]
  derivation: "Assumed: a transformer plant or expansion takes about 15 to 24 months to build (Virginia Transformer's Rincon expansion, January 2026 to March 2027; Siemens Energy's Charlotte plant due June 2027; search snippets), so 'far faster' supply can start about 2028."
spread:
  years_10_to_90:
    value: 6
    unit: years
    label: A
    sources: [vt_rincon, weg_50, wm_2030]
    derivation: "Assumed. Individual makers announce capacity increases of about 50% in 15 months (Virginia Transformer, WEG: snippets); Wood Mackenzie expects most specifications to stay in marginal shortage to 2030 on the current path. A capability that ends the wait everywhere is assumed to go from 10% to 90% of grid-connected projects in 6 years. Gives a 2035 share of about 0.57 (with max_share 0.9)."
  max_share:
    value: 0.9
    unit: "share of grid-connected projects (by value) that get their equipment without waiting"
    label: A
    sources: []
    derivation: "Assumed: special units (HVDC converters, very large or non-standard transformers, remote small grids) are about a tenth of the market and stay slow."
derivation_inputs:             # the pieces of the price, the next-best price and Q0, each with its own label and source
  m_month:
    value: 0.0075053
    unit: "2026 int$ of waiting cost per $ of project per month of waiting"
    label: E
    sources: []
    derivation: "price:CAP_INCOME / 12 = 0.0900640 / 12 (model number, input_prices.csv: (1 - labour share) x on-course output / on-course capital stock K21, E). A project's value is out of use while it waits, so each month costs the return on that value. The same number as starter 9 (permits_grid_fast), so the two entries price a month of waiting alike."
  T0_eq:
    value: 8
    unit: "months of waiting for transformers and grid equipment on the critical path of the average grid-connected project, today"
    label: A
    sources: [lbnl_iacod2008, lbnl_iacod2025, lbnl_iacod_why, iea_leadtimes, wm_leadtime128, wm_prepandemic, nrel_dist2yr]
    derivation: "Assumed. LBNL: the median US power project took 31 months from interconnection agreement to operation in 2025 against 21 in 2008 (S), 'largely due to factors outside of the interconnection process, such as procurement / offtake, permitting, and transmission completion' (S): a rise of 10 months from all these causes. Equipment lead times are well above that rise: large power transformers average 128 weeks against 30-60 weeks before the pandemic (Wood Mackenzie, snippets: 16 to 23 months more); distribution transformers up to 2 years, about four times pre-2022 (NREL, snippet); IEA: lead times for large power transformers nearly doubled (S). Projects plan around the wait (orders placed early, slots reserved), so not all of it delays them; 8 months (80% of LBNL's 10-month rise) is taken for the average grid-connected project in the world. Range 4 to 16 months."
  T1_eq:
    value: 1
    unit: "months of waiting for transformers and grid equipment on the critical path, with the capability"
    label: A
    sources: [nema_4to6, dist_1to3]
    derivation: "Assumed: 'far faster' read as equipment delivered in about a month, like distribution transformers before 2020 (4 to 6 weeks, or 1 to 3 months: snippets)."
  gen_invest_2025:
    value: 1000
    unit: "bn USD (market) a year invested in electricity generation, world, 2025"
    label: S
    sources: [iea_invest]
  dc_invest_2025:
    value: 580
    unit: "bn USD (market) invested in data centres, world, 2025"
    label: S
    sources: [iea_dc580]
  grid_invest_2035:
    value: 650
    unit: "bn USD (market) of grid-related investment, world, 2035 (IEA Current Policies Scenario)"
    label: S
    sources: [iea_grid650]
  projects_2035:
    value: 2680.7
    unit: "bn 2026 int$ a year of grid-connected power, grid and data-centre projects, on course 2035"
    label: E
    sources: [iea_invest, iea_dc580, iea_grid650]
    derivation: "(generation 1,000 + data centres 580) x 1.28524 (on-course growth of productive equipment C14, 9,062.0 / 7,050.8, model numbers) + grids 650 (IEA 2035, S) = 2,680.7 bn. Market US dollars used as international dollars (traded capital goods, E). Generation and data-centre investment are held at their 2025 level to 2026 and then grow with C14; data centres probably grow faster, so this is on the low side."
  equipment_share:
    value: 0.5
    unit: "share of these projects' value that is equipment (C14) rather than structures (C13)"
    label: A
    sources: []
    derivation: "Assumed: wind turbines, transformers, switchgear, inverters and cooling and electrical systems are most of a power or data-centre project's value; lines, foundations and buildings are the rest. Servers are mostly installed after power arrives and so do not stand idle; they are left out by taking a half rather than more."
demand:
  - id: d1
    good: "new:equipment_wait"     # red team fix RT21: was C14. The price here is a waiting cost per $ of equipment,
    layer: C14                     # not the price of C14; its own good key keeps it from being combined as a rival
    mode: cost                     # option with a cost curve on C14's own price (decisions D3.5), as for permits_grid_fast
    quantity_unit: "$ of equipment (C14) in grid-connected power, grid and data-centre projects a year, at today's equipment prices"
    P0: {use: next_best}
    P1: {use: price}
    Q0:
      model: "oc:C14"
      factor:
        value: 1.4791e8
        unit: "$ of equipment in grid-connected projects per bn of C14 output"
        label: A
        sources: [iea_invest, iea_dc580, iea_grid650]
        derivation: "equipment_share 0.5 [A] x projects_2035 2,680.7 bn [E] / on-course C14 9,062.0 bn x 1e9 = 1.4791e8 (14.8% of on-course productive equipment). A because the equipment share is assumed."
    elasticity:
      value: -0.022657
      unit: "% change in grid-connected projects bought per 1% change in the waiting cost"
      label: A
      sources: [labandeira2017]
      derivation: "Buyers respond to the full price of a project, 1 + c (its cost plus the cost of waiting). The elasticity with respect to the waiting cost c is the project's price elasticity times c0 / (1 + c0) = -0.4 x 0.060043 / 1.060043 = -0.022657. -0.4 is assumed: demand for power plants, grids and data centres is derived from electricity demand, which is price-inelastic in the short and long run (Labandeira, Labeaga and Lopez-Otero 2017 meta-analysis, snippet; numbers not seen). This curve carries the extra projects started because waiting is cheaper; the extra electricity they make is not valued again (it costs resources to make)."
      evidence_price_range: [0.0, 0.060043]
    limit:
      value: 9.062e12
      unit: "$ of equipment (C14) a year"
      label: E
      sources: []
      derivation: "On-course 2035 output of the productive-equipment layer C14 (9,062.0 bn, model number) x 1e9: grid-project equipment cannot exceed all productive equipment."
      description: "Grid-project equipment cannot exceed the whole C14 layer. The evidence range covers the whole sweep: removing the waiting cost lowers a project's full price by at most 5.7%. Near zero the constant-elasticity curve gives about 1.10 x Q0 at a waiting cost of 0.001, well below the limit."
changes:
  - id: ch2
    kind: supply
    input: K21
    add:
      value: 1.5637
      unit: "tn 2026 int$ (PPP) of capital stock in 2035"
      label: A
      sources: [iea_invest, iea_dc580, iea_grid650]
      derivation: "Capital no longer standing idle: (T0 - T1) / 12 x projects_2035 = (8 - 1) / 12 x 2,680.7 bn = 1,563.7 bn = 1.5637 tn. The whole project (structures and equipment) is idle while it waits, so both parts are counted here. A because T0 and T1 are assumed."
    scale_with: adoption
    mechanism: "Projects that wait for equipment hold capital that produces nothing; delivered sooner, the same capital stock supports more output, so the usable capital stock K21 rises on path (b). This is the same mechanism as demand d1 carried to path (b) (d1 values it on path a); it is a change, not a knock-on, so path (a) does not value it again."
knock_ons: []
gva_share:
  value: 0.35
  unit: "value added per $ of sales"
  label: A
  sources: []
  derivation: "Assumed: electrical-equipment manufacturing buys much of its value in materials (electrical steel, copper, oil, insulation); about a third of its sales is value added. Note: the engine's sales base for this entry is the waiting cost paid at the capability's price, not the equipment makers' sales."
capital_per_output:
  value: 0.8
  unit: "$ of capital per $ of output a year"
  label: A
  sources: [hitachi_varennes]
  derivation: "Assumed: transformer factories need winding and core lines, vapour-phase ovens and high-voltage test bays; announced expansions (for example Hitachi Energy, CAD 270 million to nearly triple large-power-transformer capacity at Varennes, snippet) suggest less than a dollar of capital per dollar of yearly output."
value_beyond_gdp:
  - what: "Carbon dioxide avoided when generation that waits for transformers (mostly wind and solar) is connected and replaces fossil generation (shown beside the result, never added; overlaps starter 9's figure for the same held-up projects)"
    quantity:
      value: 1.2045e9
      unit: "t CO2 a year"
      label: A
      sources: []
      derivation: "1,720.7 TWh a year (the on-course generation that on-course transformer supply cannot connect, K01 minus K14 on course, model_ids.md) x 0.7 t CO2 per MWh of fossil generation displaced (assumed: coal about 1.0, gas about 0.4)."
    value_per_unit:
      value: 240
      unit: "2026 int$ per t CO2"
      label: A
      sources: [scc_epa]
      derivation: "EPA 2023 social cost of carbon, $190 per t in 2020 dollars at a 2% discount rate, about $240 in 2026 dollars (search snippet, as used by starter 9)."
published_estimates:
  - claim: "IEA (2023), Electricity Grids and Secure Energy Transitions, Grid Delay Case: if grids are not built in time, cumulative power-sector CO2 emissions to 2050 are 58 Gt higher than in the scenario aligned with national climate targets, mainly through slower solar and wind. Not a GDP figure; recorded for scale."
    value: 58
    unit: "Gt CO2, cumulative to 2050 (world)"
    scale: "world, 2030-2050, grids delayed (all causes, not only equipment)"
    sources: [iea_griddelay]
  - claim: "Wood Mackenzie (2025): supply deficit of about 30% for power transformers and 10% for distribution transformers in 2025, persisting into the 2030s (US market). The size of the shortage, not of its economic cost."
    value: 30
    unit: "% of US power-transformer demand not met, 2025"
    scale: "country (US), 2025"
    sources: [wm_deficit]
  - claim: "Trade press (2025-26): about 7 GW of planned US AI data-centre capacity delayed or cancelled because of power-infrastructure constraints (transformers and turbines among them)."
    value: 7
    unit: "GW of US data-centre capacity delayed or cancelled"
    scale: "country (US), 2025-2026, all power-infrastructure causes"
    sources: [dc_7gw]
not_mapped:
  - "Transformers and grid equipment (K14) are not an input in stage1-v5 (their need copies K01's), so the machine cannot lift their supply directly. stage1-v5/not_inputs.csv shows K14's record-pace supply (73,055 TWh) is below the need at the target (74,393 TWh): counted as an input it would bind at a world growth of about 7.8% a year. Removing that latent limit is this capability's main path (b) effect, and no model number carries it (validate.py forbids a cap or supply change on K14). Today it binds after robots, cropland, capital, construction trades and licensing, so it would matter only in pairs that relieve those."
  - "The structures part (C13) of the projects that wait for equipment (about half of 2,680.7 bn a year in 2035) is left out of the demand curve. Starter 9 (permits_grid_fast) has a cost curve on C13 with a different old price; the engine combines two cost curves on one good as alternatives sharing one old price, which would mis-combine the pair. Counting it would roughly double d1. The main agent may decide how to carry it."
  - "The fall in equipment prices: power transformer prices almost doubled since 2019 (IEA), 60-80% since January 2020 (Wood Mackenzie, snippet), mostly because of factory bottlenecks. On equipment bought anyway that fall is a transfer from makers to buyers, not a gain. The extra equipment bought at the lower price is a small triangle (about 4% of grid-equipment sales at an elasticity of -0.4) that overlaps d1's extra projects; not counted."
  - "Data centres connected sooner (more AI compute K05): IEA says about 20% of projected data-centre additions to 2030 are at risk of delay because of grid queues and equipment supply together. Starter 9 already carries that whole figure as its knock-on k1; it is not repeated here, to avoid counting the same delay twice."
  - "Cheaper electricity for every layer once held-up wind and solar connect: the machine's electricity price is a fixed US retail price; no model number carries the fall."
  - "Faster repair after storms and failures (spare transformers in stock): fewer and shorter outages. No model number for reliability."
  - "Copper and grain-oriented electrical steel needed for the extra transformers: copper was about 10% of a power transformer's price in 2023 (IEA). The extra copper is small next to K06 supply and is not added as a need."
  - "Distribution transformers for new housing, factories and charging hubs outside power, grid and data-centre projects are not in Q0 (no sourced value)."
  - "Removed by the red team (RT18): a change ch1 added 1,720.7 TWh a year to K01's supply (K01 on course 44,274.0 minus K14 on course 42,553.3 TWh: the generation on-course transformer supply could not connect). In the model neither K01's on-course nor its record-pace supply is cut by the transformer shortfall (K14 is not an input; K14's record pace, 73,055 TWh, is far below K01's, 93,252, and path b uses K01's in full), so that generation is already in K01's supply and adding it counted it twice. K01 does not bind before the target, so the removal moves no result on its own; it stops the entry offsetting electricity_cheap's extra K01 use in a pair, and stops a double count with permits_grid_fast's K01 change for the same held-up projects."
  - "Red team note (RT19): ch2 counts the whole of projects_2035 as idle while it waits, including the IEA's data-centre investment, which may include servers that are installed after power arrives (d1 leaves them out through equipment_share 0.5); ch2 may be somewhat high."
refused: false
refusal: ""
sources:
  # --- saved copies in the repository (copied to stage1-v7/sources/) ---
  - id: iea_invest
    title: "IEA, World Energy Outlook 2025 (investment in generation and grids); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "Investments in electricity generation have charged ahead by almost 70% since 2015 to reach USD 1 trillion per year, but annual grid spending has risen at less than half the pace to USD 400 billion."
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 1
    kind: statistics
    published: 2025
  - id: iea_dc580
    title: "IEA, World Energy Outlook 2025 (investment in data centres); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "Investment in data centres is expected to reach USD 580 billion in 2025."
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 1
    kind: statistics
    published: 2025
  - id: iea_grid650
    title: "IEA, World Energy Outlook 2025, chapter 3 (grid investment needs, Current Policies Scenario); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "with annual grid-related investment spending reaching about USD 650 billion in 2035."
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 2
    kind: forecast
    published: 2025
  - id: iea_leadtimes
    title: "IEA, World Energy Outlook 2025, chapter 3 (grid supply chains); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "Lead times for large power transformers and high-voltage cables have nearly doubled in many regions and wait times for HVDC systems stretch into the 2030s."
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 1
    kind: statistics
    published: 2025
  - id: iea_pricedelivery
    title: "IEA, World Energy Outlook 2025, chapter 4 (grids); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "especially for critical components like transformers, which have seen prices and delivery times nearly double in recent years"
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 1
    kind: statistics
    published: 2025
  - id: iea_dc_backlog
    title: "IEA, World Energy Outlook 2025, chapter 1 (data centres); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_weo2025/weo2025.txt"
    url: "https://iea.blob.core.windows.net/assets/0a7a40a4-5dcb-4d6e-a7ad-76a1c90ec8eb/WorldEnergyOutlook2025.pdf"
    accessed: "2026-11-18"
    quote: "the backlog for the delivery of transformers has been lengthening, impacting the rollout of infrastructure catering to data centre construction."
    saved_copy: "sources/grid_equipment_fast__iea_weo2025.txt"
    sha256: "6244c47677ac73062ab82ca02a83840bcdf6f3d13691495ce235a6dda4bbe09d"
    strength: 1
    kind: statistics
    published: 2025
  - id: iea_gcmo_price
    title: "IEA, Global Critical Minerals Outlook 2026, chapter 3 (copper in transformers and cables); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_gcmo2026/gcmo2026.txt"
    url: "https://iea.blob.core.windows.net/assets/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf"
    accessed: "2026-11-18"
    quote: "Prices for power transformers have almost doubled since 2019, predominantly due to manufacturing bottlenecks and insufficient production capacity to meet surging demand from grid development."
    saved_copy: "sources/grid_equipment_fast__iea_gcmo2026.txt"
    sha256: "fd7582363329f70e8bfff9c8ad3741c9a18824d6cf6aa2f62435b6260b1bc45c"
    strength: 1
    kind: statistics
    published: 2026
  - id: iea_gcmo_copper
    title: "IEA, Global Critical Minerals Outlook 2026, chapter 3 (copper share of transformer price); saved copy from stage1-v2/agent4_bottlenecks/raw/iea_gcmo2026/gcmo2026.txt"
    url: "https://iea.blob.core.windows.net/assets/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf"
    accessed: "2026-11-18"
    quote: "In 2023, copper comprised around 10% of the power transformer price"
    saved_copy: "sources/grid_equipment_fast__iea_gcmo2026.txt"
    sha256: "fd7582363329f70e8bfff9c8ad3741c9a18824d6cf6aa2f62435b6260b1bc45c"
    strength: 1
    kind: statistics
    published: 2026
  - id: lbnl_iacod2008
    title: "LBNL, Queued Up: 2026 Edition (Rand et al., June 2026), interconnection agreement to commercial operation; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_queued_up_2026/q.txt"
    url: "https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf"
    accessed: "2026-11-18"
    quote: "The median was 21 months in 2008"
    saved_copy: "sources/grid_equipment_fast__lbnl_queued_up_2026.txt"
    sha256: "b5d1ec6c43dbcb41abffaa4d51a1709bdf92c92042138427687d1437867697ca"
    strength: 1
    kind: statistics
    published: 2026
  - id: lbnl_iacod2025
    title: "LBNL, Queued Up: 2026 Edition, interconnection agreement to commercial operation; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_queued_up_2026/q.txt"
    url: "https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf"
    accessed: "2026-11-18"
    quote: "The median was 31 months in 2025"
    saved_copy: "sources/grid_equipment_fast__lbnl_queued_up_2026.txt"
    sha256: "b5d1ec6c43dbcb41abffaa4d51a1709bdf92c92042138427687d1437867697ca"
    strength: 1
    kind: statistics
    published: 2026
  - id: lbnl_iacod_why
    title: "LBNL, Queued Up: 2026 Edition, causes of long agreement-to-operation times; saved copy from stage1-v2/v1/agent4_bottlenecks/raw/lbnl_queued_up_2026/q.txt"
    url: "https://eta-publications.lbl.gov/sites/default/files/2026-06/queued_up_2026_edition.pdf"
    accessed: "2026-11-18"
    quote: "Long timelines from IA to COD are largely due to factors outside of the interconnection process, such as procurement / offtake, permitting, and transmission completion"
    saved_copy: "sources/grid_equipment_fast__lbnl_queued_up_2026.txt"
    sha256: "b5d1ec6c43dbcb41abffaa4d51a1709bdf92c92042138427687d1437867697ca"
    strength: 1
    kind: statistics
    published: 2026
  # --- found only by web search: no saved copy (see sources/pending_grid_equipment_fast.csv); numbers from them are A ---
  - id: wm_leadtime128
    title: "Wood Mackenzie, power transformer lead times (Q2 2025 survey), as reported in search results; search snippet only"
    url: "https://www.woodmac.com/news/opinion/mind-the-gap-tackling-supply-chain-challenges-in-the-electric-td-sector/"
    accessed: "2026-11-18"
    quote: "Power transformer lead times eased in Q2 falling by 10 weeks to an average of 128 weeks."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: wm_prepandemic
    title: "Wood Mackenzie, 'Supply shortages and an inflexible market give rise to high power transformer lead times'; search snippet only"
    url: "https://www.woodmac.com/news/opinion/supply-shortages-and-an-inflexible-market-give-rise-to-high-power-transformer-lead-times/"
    accessed: "2026-11-18"
    quote: "pre-pandemic lead times ranged from 30–60 weeks, depending on specifications/size"
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2024
  - id: wm_prices
    title: "Wood Mackenzie, 'Supply shortages and an inflexible market give rise to high power transformer lead times'; search snippet only"
    url: "https://www.woodmac.com/news/opinion/supply-shortages-and-an-inflexible-market-give-rise-to-high-power-transformer-lead-times/"
    accessed: "2026-11-18"
    quote: "transformer prices have risen 60% to 80% on average since January 2020"
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2024
  - id: wm_deficit
    title: "Wood Mackenzie (September 2025), power and distribution transformer supply deficit, as reported in search results; search snippet only"
    url: "https://www.powermag.com/wp-content/uploads/2026/01/making-the-connection-executive-summary-september-2025.pdf"
    accessed: "2026-11-18"
    quote: "Wood Mackenzie projected supply shortages could reach 30% for power transformers and 10% for distribution transformers by 2025"
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: wm_2030
    title: "Wood Mackenzie, transformer market outlook, as reported in search results; search snippet only"
    url: "https://www.woodmac.com/news/opinion/supply-shortages-and-an-inflexible-market-give-rise-to-high-power-transformer-lead-times/"
    accessed: "2026-11-18"
    quote: "Wood Mackenzie expects most specifications in the market will remain in a marginal shortage by 2030."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2024
  - id: nrel_dist2yr
    title: "NREL (2024), Major Drivers of Long-Term Distribution Transformer Demand (NREL/TP-6A40-87653); search snippet only"
    url: "https://www.nrel.gov/docs/fy24osti/87653.pdf"
    accessed: "2026-11-18"
    quote: "utilities face extended lead times for transformers of up to 2 years (a fourfold increase on pre-2022 lead times)"
    saved_copy: ""
    sha256: ""
    strength: 2
    kind: study
    published: 2024
  - id: nema_4to6
    title: "Utility Dive, electric transformer shortage (NREL, NIAC), quoting a NEMA official; search snippet only"
    url: "https://www.utilitydive.com/news/electric-transformer-shortage-nrel-niac/738947/"
    accessed: "2026-11-18"
    quote: "A NEMA official put the wait at four to six weeks roughly five years earlier than 2024."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2024
  - id: dist_1to3
    title: "Trade press on distribution transformer procurement before the shortage; search snippet only"
    url: "https://www.fastcompany.com/91442349/supply-chain-delays-transformers-push-power-grid"
    accessed: "2026-11-18"
    quote: "the one-to-three months it used to take to procure a distribution transformer, which then grew to two years or more"
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: vt_rincon
    title: "Virginia Transformer, Rincon (Georgia) expansion, as reported by Supply Chain Dive (press release, 2025-11-20); search snippet only"
    url: "https://www.supplychaindive.com/press-release/20251120-virginia-transformer-to-expand-georgia-transformer-plant-in-rincon-ga-to/"
    accessed: "2026-11-18"
    quote: "The expansion will increase installed capacity there by 50 percent, and will be completed in March of 2027."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: weg_50
    title: "WEG US transformer capacity investment, as reported in search results; search snippet only"
    url: "https://www.tdworld.com/utility-business/news/55412969/powering-the-grid-manufacturers-boost-north-american-transformer-supply-capabilities-through-stronger-domestic-investments"
    accessed: "2026-11-18"
    quote: "WEG announced a $77 million investment to increase its U.S. transformer production capacity by 50% through vertical integration and automation."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: siemens_charlotte
    title: "Siemens Energy large power transformer plant, Charlotte NC, as reported in search results; search snippet only"
    url: "https://enkiai.com/data-center/siemens-energy-power-transformer-2027-421m-nc-plant/"
    accessed: "2026-11-18"
    quote: "Siemens Energy has a $421 million investment for a new large power transformer facility in Charlotte, North Carolina, set for completion in June 2027."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: hitachi_varennes
    title: "Hitachi Energy, Varennes (Quebec) transformer investment, as reported in search results; search snippet only"
    url: "https://www.utilitydive.com/news/hitachi-energy-expands-transformer-factories-pennsylvania-virginia-mexico/728308/"
    accessed: "2026-11-18"
    quote: "the planned developments could nearly triple large power transformer production capacity, Hitachi says."
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2025
  - id: labandeira2017
    title: "Labandeira, Labeaga and Lopez-Otero (2017), A meta-analysis on the price elasticity of energy demand, Energy Policy 102, 549-568; search snippet only (electricity coefficients not seen)"
    url: "https://econpapers.repec.org/RePEc:eee:enepol:v:102:y:2017:i:c:p:549-568"
    accessed: "2026-11-18"
    quote: "The authors report that energy goods are price-inelastic in both the short and long run."
    saved_copy: ""
    sha256: ""
    strength: 2
    kind: study
    published: 2017
  - id: iea_griddelay
    title: "IEA (2023), Electricity Grids and Secure Energy Transitions, executive summary (Grid Delay Case); search snippet only"
    url: "https://www.iea.org/reports/electricity-grids-and-secure-energy-transitions/executive-summary"
    accessed: "2026-11-18"
    quote: "cumulative CO2 emissions from the power sector to 2050 would be 58 gigatonnes higher in the Grid Delay Case than in a scenario aligned with national climate targets"
    saved_copy: ""
    sha256: ""
    strength: 2
    kind: forecast
    published: 2023
  - id: dc_7gw
    title: "EnkiAI, 'Power Transformer Shortages Delay 7 GW of AI Projects and 2,500 GW of Renewables (2025 to 2026)'; search snippet only"
    url: "https://enkiai.com/data-center/grid-shortage-pjm-ercot-data/"
    accessed: "2026-11-18"
    quote: "7 GW of planned U.S. AI data center capacity either delayed or canceled specifically due to power infrastructure constraints"
    saved_copy: ""
    sha256: ""
    strength: 3
    kind: claim
    published: 2026
  - id: scc_epa
    title: "Resources for the Future, Report 26-11 (EPA 2023 social cost of carbon in 2026 dollars); search snippet only (the same source and quote as starter 9)"
    url: "https://media.rff.org/documents/Report_26-11_Final.pdf"
    accessed: "2026-11-18"
    quote: "the $190 value (in 2020 dollars) is equivalent to about $240 in 2026 dollars"
    saved_copy: ""
    sha256: ""
    strength: 2
    kind: study
    published: 2023